Alabama mechanic's liens
Mechanic's Liens in Alabama — Sources checked
Who and what this applies to
Private real-property mechanics’ liens under Alabama Code §§35-11-210 through 35-11-221; the claimant’s role controls filing and notice obligations.
The rules
- File a verified lien statement with the probate judge in the property county, stating the credited amount, identifying the property and naming its owner, as required by §35-11-213. Source
- Section 35-11-215 requires original contractors to file within six months, journeymen and day laborers within 30 days, and other claimants within four months after the last covered labor or furnishing. Source
- Before filing, claimants other than the original contractor must give the owner the written amount, basis and debtor notice under §35-11-218; that section excepts materials already covered by the advance notice in §35-11-210. Source
- Section 35-11-221 generally requires enforcement within six months after maturity of the entire secured debt, subject to exceptions in the division. Source
Primary sources
Sources reviewed 2026-09-30. This guide covers the projects and rules stated above.
Not legal advice. This is general legal information. Laws and project facts differ; confirm the applicable requirements for your project.