Alabama prompt payment

Prompt Payment in Alabama — Sources checked

Who and what this applies to

Private construction within Alabama Code chapter 8-29. Section 8-29-7 excludes residential homebuilders, residential improvements of 16 or fewer units, contracts/subcontracts/sub-subcontracts of $10,000 or less, and state or local government contracts.

The rules

  • For performance and requests satisfying §8-29-3(a), the owner pays according to the payment terms specified in the contract documents, or within 30 days after receipt if no terms are agreed. Source
  • Sections 8-29-3(b)–(c) address agreed downstream terms and a seven-day receipt-based default. Section 8-29-3(e) separately requires a contractor receiving owner payment to pass each subcontractor its attributable share, including attributable interest, by the seventh day after receipt. Source
  • Noncompliant late payment bears interest of 1% per month on the unpaid balance due. Statutory and contractual grounds for withholding remain relevant. Source

Deadlines

Owner default: 30 days after receipt; downstream receipt-based rule: seven days, as described.

Primary sources

Sources reviewed 2026-09-30. This guide covers the projects and rules stated above.

Not legal advice. This is general legal information. Laws and project facts differ; confirm the applicable requirements for your project.

Back to Alabama contractor law · Prompt Payment topic guide.

Related tools and support

Visit GC Experts for contractor business support. FedTrakker currently leads to the GC Experts site. For project-specific legal advice, find counsel.

Explore the $29 state packs and included templates.