Alaska mechanic's liens

Mechanic's Liens in Alaska — Sources checked

Who and what this applies to

Recording deadlines and contents under AS 34.35.068–.071; notice-of-completion procedures can shorten the ordinary period.

The rules

  • Without an effective notice of completion, §34.35.068(a) gives a claimant 120 days after completing the claimant’s contract or ceasing the covered labor, services, materials or equipment to record a lien claim. Source
  • A properly noticed and recorded notice of completion can require affected claimants to record a lien claim or notice of right to lien within 15 days. A timely notice of right preserves the ordinary 120-day filing period. The result depends on the claimant’s prior notice and whether the owner gave the required advance notice under §§34.35.068(b) and .071. Source
  • The verified recorded claim must contain the information in §34.35.070, including the claimant, owner, contracting party, property description, contract amount, amount due and last furnishing date. Source

Primary sources

Sources reviewed 2026-09-30. This guide covers the projects and rules stated above.

Not legal advice. This is general legal information. Laws and project facts differ; confirm the applicable requirements for your project.

Back to Alaska contractor law · Mechanic's Liens topic guide.

Related tools and support

Visit GC Experts for contractor business support. FedTrakker currently leads to the GC Experts site. For project-specific legal advice, find counsel.

Explore the $29 state packs and included templates.