Alaska retainage

Retainage in Alaska — Sources checked

Who and what this applies to

State public construction/public works; political subdivisions are covered when they have the written state-funding contract required by AS 36.90.265.

The rules

  • The prime’s subcontract must require payment of retainage due within eight working days after the later of receipt of final state/subdivision payment or expiration of the AS 36.25.020(b) notice period. Source
  • A subcontractor must pass retainage due to its lower tier within eight working days after receiving its share of state-held retainage. Performance-related withholding remains subject to §§36.90.220–.240. Source

Primary sources

Sources reviewed 2026-09-30. This guide covers the projects and rules stated above.

Not legal advice. This is general legal information. Laws and project facts differ; confirm the applicable requirements for your project.

Back to Alaska contractor law · Retainage topic guide.

Related tools and support

Visit GC Experts for contractor business support. FedTrakker currently leads to the GC Experts site. For project-specific legal advice, find counsel.

Explore the $29 state packs and included templates.