Arizona retainage
Retainage in Arizona — Sources checked
Who and what this applies to
Public contracts governed by A.R.S. §34-221(C); these rules are not stated as private-project caps.
The rules
- The public progress-payment provision permits retention of 10%. At 50% completion, the contractor may request release of half the accumulated retention; release depends on satisfactory progress and the absence of a specific cause or claim requiring greater retention. Source
- After that reduction, subsequent retention is limited to 5% while progress remains satisfactory. Unsatisfactory progress permits the statutory restoration of 10% retention. Source
- Retained amounts are due within 60 days after completion and filing of the notice of completion. A longer period requires the specific written finding under §34-221(C)(5), and withholding is limited to the amount necessary for the identified purpose. Source
Primary sources
Sources reviewed 2026-09-30. This guide covers the projects and rules stated above.
Not legal advice. This is general legal information. Laws and project facts differ; confirm the applicable requirements for your project.
Back to Arizona contractor law · Retainage topic guide.