California mechanic's liens
Mechanic's Liens in California — Sources checked
Who and what this applies to
Direct-contractor recording period under Civil Code §8412; this paragraph does not supply a subcontractor’s recording or preliminary-notice rules.
The rules
- A direct contractor records a lien claim after completing the direct contract and before the earlier of 90 days after completion of the work of improvement or 60 days after the owner records a notice of completion or cessation. Source
Primary sources
Sources reviewed 2026-09-30. This guide covers the projects and rules stated above.
Not legal advice. This is general legal information. Laws and project facts differ; confirm the applicable requirements for your project.