California prompt payment
Prompt Payment in California — Sources checked
Who and what this applies to
Private progress payments under Civil Code §8800 and public-project downstream payments under Public Contract Code §10262.5.
The rules
- Unless otherwise agreed in writing, an owner pays a qualifying contractual private progress payment within 30 days after notice demanding payment. A good-faith dispute permits withholding no more than 150% of the disputed amount; wrongful withholding carries the statutory 2% monthly penalty. Source
- On covered public work, a prime contractor or subcontractor pays its subcontractor within seven days after receiving the corresponding progress payment. A good-faith dispute permits withholding no more than 150% of the disputed amount; wrongful withholding carries a 2% monthly penalty under §10262.5. Source
Primary sources
Sources reviewed 2026-09-30. This guide covers the projects and rules stated above.
Not legal advice. This is general legal information. Laws and project facts differ; confirm the applicable requirements for your project.
Back to California contractor law · Prompt Payment topic guide.