Connecticut retainage

Retainage in Connecticut — Sources checked

Who and what this applies to

Private construction within C.G.S. §42-158i. Excluded: contracts with the listed federal/state/local public entities, HUD-funded or HUD-insured projects, owner-contractor contracts of $25,000 or less and resulting subcontracts, and residential buildings of four or fewer units.

Thresholds and scope

5% for covered private contracts.

The rules

  • Section 42-158k caps contractual retainage at 5% of estimated progress payments throughout the project. Source
  • The owner must pay all retainage within 30 days after the certificate of final completion from the owner/authorized representative or equivalent written acceptance by the owner. Source

Primary sources

Sources reviewed 2026-09-30. This guide covers the projects and rules stated above.

Not legal advice. This is general legal information. Laws and project facts differ; confirm the applicable requirements for your project.

Back to Connecticut contractor law · Retainage topic guide.