Delaware mechanic's liens
Mechanic's Liens in Delaware — Sources checked
Who and what this applies to
Statement-of-claim filing under 25 Del. C. §§2711–2712; claimant category and statutory completion alternatives control.
The rules
- A person contracting directly with the owner who supplies both labor and materials, and a covered construction manager, generally has 180 days after structure completion to file. Section 2711(a)(2) supplies alternative dates that establish timely filing, including its specified contract-completion, payment, invoice, occupancy and acceptance events. Source
- Other covered claimants generally file within 120 days after the last labor or material delivery. Section 2711(b) also has alternative final-payment triggers; do not substitute a universal 120-day period for the category-specific statute. Source
- The verified statement of claim is filed with the Prothonotary of the Superior Court in the property county and must contain the information required by §2712. Source
Primary sources
Sources reviewed 2026-09-30. This guide covers the projects and rules stated above.
Not legal advice. This is general legal information. Laws and project facts differ; confirm the applicable requirements for your project.
Back to Delaware contractor law · Mechanic's Liens topic guide.
Related tools and support
Visit GC Experts for contractor business support. FedTrakker currently leads to the GC Experts site. For project-specific legal advice, find counsel.