Delaware retainage

Retainage in Delaware — Sources checked

Who and what this applies to

Limited to the construction category and statutory provision described below.

The rules

  • For public construction governed by Delaware Code §6962, an agency retains 5% of completed-work value as specified in the bid documents. At completion, it may release 60% of the retained amount. Final release is subject to the section’s approval, reporting and subcontractor-payment requirements; disputed payments can justify additional withholding under the statute. Source

Primary sources

Sources reviewed 2026-09-30. This guide covers the projects and rules stated above.

Not legal advice. This is general legal information. Laws and project facts differ; confirm the applicable requirements for your project.

Back to Delaware contractor law · Retainage topic guide.

Related tools and support

Visit GC Experts for contractor business support. FedTrakker currently leads to the GC Experts site. For project-specific legal advice, find counsel.

Explore the $29 state packs and included templates.