Hawaii prompt payment

Prompt Payment in Hawaii — Sources checked

Who and what this applies to

Limited to the construction category and statutory provision described below.

The rules

  • On Hawaii public contracts governed by HRS §103-10.5, the contractor must pay a subcontractor within ten days after receiving the corresponding disbursement if the subcontract terms are met and there is no qualifying bona fide dispute. Final subcontractor retainage is likewise due within ten days after the prime receives final payment when the section’s conditions are satisfied. Source

Primary sources

Sources reviewed 2026-09-30. This guide covers the projects and rules stated above.

Not legal advice. This is general legal information. Laws and project facts differ; confirm the applicable requirements for your project.

Back to Hawaii contractor law · Prompt Payment topic guide.

Related tools and support

Visit GC Experts for contractor business support. FedTrakker currently leads to the GC Experts site. For project-specific legal advice, find counsel.

Explore the $29 state packs and included templates.