Idaho retainage
Retainage in Idaho — Sources checked
Who and what this applies to
Public construction within Idaho Code §54-1926(3).
The rules
- When a public body requires a performance bond or a payment bond exceeding 50% of the contract amount, it may withhold no more than 5% of the total payable as retainage. It must release retainage for portions accepted by the public body and contractor as complete within 30 days of that acceptance. Source
- A public-work contractor may withhold no more than 5% of the amount payable to a subcontractor and must remit that retainage within 30 days after completion of the subcontract. Source
Primary sources
Sources reviewed 2026-09-30. This guide covers the projects and rules stated above.
Not legal advice. This is general legal information. Laws and project facts differ; confirm the applicable requirements for your project.
Back to Idaho contractor law · Retainage topic guide.