Louisiana retainage

Retainage in Louisiana — Sources checked

Who and what this applies to

Public works executed under the statutory part covered by La. R.S. 38:2248; the Department of Transportation and Development is excluded.

Thresholds and scope

Withholding caps: 10% of contract price below $500,000; 5% at $500,000 or more.

The rules

  • Section 2248(A) limits contractual withholding to the stated caps until expiration of 45 days after recording formal acceptance or notice of contractor/subcontractor default. Source
  • Punch lists must include estimated correction costs. The agency may not withhold more than the punch-list value; completed items are paid after the 45-day lien period. The section cannot be waived and does not apply to DOTD. Source
  • Subsection C separately permits contractual liquidated-damage withholding on specified flood and integrated coastal-protection projects after the statutory period, considering granted time extensions. Source

Primary sources

Sources reviewed 2026-09-30. This guide covers the projects and rules stated above.

Not legal advice. This is general legal information. Laws and project facts differ; confirm the applicable requirements for your project.

Back to Louisiana contractor law · Retainage topic guide.

Related tools and support

Visit GC Experts for contractor business support. FedTrakker currently leads to the GC Experts site. For project-specific legal advice, find counsel.

Explore the $29 state packs and included templates.