Maine retainage
Retainage in Maine — Sources checked
Who and what this applies to
Construction contracts under Title 10, chapter 201-A, including covered public owners. Department of Transportation contracts and material purchases by a person working on their own property are excluded (§§1111, 1112, 1120).
Thresholds and scope
Section 1116 sets release rules rather than a retainage percentage.
The rules
- Retainage due upon completion must be paid within 30 days after final acceptance. If the owner holds none for a sub’s work, the contractor may retain as agreed but must pay it within 30 days of final acceptance. Source
- Notwithstanding a contrary agreement, retainage received must pass to the sub/supplier entitled to it within seven days. Unreasonable withholding of acceptance or failure to pay invokes the chapter’s interest, penalty and fee provisions. Source
- The chapter excludes DOT contracts and owners’ own-work material purchases. Source
- Own-property material-purchase contracts are excluded. Source
- Covered owners include the State and its subdivisions. Source
Primary sources
Sources reviewed 2026-09-30. This guide covers the projects and rules stated above.
Back to Maine contractor law · Retainage topic guide.
Related tools and support
Visit GC Experts for contractor business support. FedTrakker currently leads to the GC Experts site. For project-specific legal advice, find counsel.