Prompt Payment in Maryland — Sources checked
Who and what this applies to
Real Property section 9-302 payment rules, subject to section 9-305 exclusions. The owner-payment paragraph excludes contracts with the listed governmental owners.
Thresholds and scope
Section 9-305 excludes single-family construction-and-sale contracts, Custom Home Protection Act transactions and licensed MHIC home-improvement contracts.
The rules
- When the contract specifies payment dates/times, the private owner pays undisputed amounts within seven days after that date/time. Only when it specifies no dates/times does the earlier-of-30-days-after-occupancy-permit-or-possession rule apply. Source
- For a contract not with the owner, the contractor/subcontractor pays undisputed amounts to its subcontractors within seven days after receipt of the payment attributable to their work/materials. Source
- The subtitle’s residential exclusions are set out in section 9-305. Source
Primary sources
Sources reviewed 2026-09-30. This guide covers the projects and rules stated above.
Back to Maryland contractor law · Prompt Payment topic guide.
Related tools and support
Visit GC Experts for contractor business support. FedTrakker currently leads to the GC Experts site. For project-specific legal advice, find counsel.