Massachusetts mechanic's liens
Mechanic's Liens in Massachusetts — Sources checked
Who and what this applies to
Private-property written-contract liens under chapter 254, sections 2 and 4.
Thresholds and scope
Project completion and termination notices may shorten the filing period.
The rules
- For an owner-contract lien, record notice of contract by the earliest of 60 days after substantial-completion notice, 90 days after termination notice, or 90 days after the last furnishing by the claimant or anyone through or under the claimant. Source
- Section 4 claimants record notice and give the owner actual notice; their lien is subject to upstream unpaid-balance limits. The section provides the project-based notice deadline and a 30-day notice-of-identification route for claimants without a direct relationship with the original contractor, with the stated labor exception. Source
- For sections 2 and 4 liens, the statement of account is due by the earliest of 90 days after substantial-completion notice, 120 days after termination notice, or 120 days after the specified project furnishing event. Source
- Commence the enforcement civil action within 90 days after filing the section 8 statement or the lien dissolves. Source
Primary sources
Sources reviewed 2026-09-30. This guide covers the projects and rules stated above.
Not legal advice. This is general legal information. Laws and project facts differ; confirm the applicable requirements for your project.
Back to Massachusetts contractor law · Mechanic's Liens topic guide.
Related tools and support
Visit GC Experts for contractor business support. FedTrakker currently leads to the GC Experts site. For project-specific legal advice, find counsel.