Michigan prompt payment

Prompt Payment in Michigan — Sources checked

Who and what this applies to

Covered written public-agency construction contracts under 1980 PA 524: at least $30,000 and more than three payments. The public-agency definition excludes MDOT, school districts, junior/community colleges, MSHDA and municipal electric utilities/agencies.

Thresholds and scope

Progress-payment deadlines are tied to certification and receipt of government funding.

The rules

  • Section 1561 establishes the contract threshold, payment-count condition and excluded public agencies. Source
  • Pay a requested progress payment by the later of 30 days after architect/engineer certification that the covered work is in place or 15 days after receipt of the federal/state funds when funding comes from those sources. Source
  • Processing may await prior-sequence work required by the contract; if payment is late, the designated requester may include reasonable interest in the next payment request. Source

Primary sources

Sources reviewed 2026-09-30. This guide covers the projects and rules stated above.

Not legal advice. This is general legal information. Laws and project facts differ; confirm the applicable requirements for your project.

Back to Michigan contractor law · Prompt Payment topic guide.