Michigan retainage

Retainage in Michigan — Sources checked

Who and what this applies to

Covered written public-agency construction contracts under 1980 PA 524: at least $30,000 and more than three payments. The public-agency definition excludes MDOT, school districts, junior/community colleges, MSHDA and municipal electric utilities/agencies.

Thresholds and scope

Maximum 10% through 50% work-in-place; continued withholding requires the statutory performance grounds.

The rules

  • Coverage and excluded agencies are specified in section 1561. Source
  • An agency may retain up to 10% of work-in-place through 50% completion. Thereafter it may retain up to 10% of further work only for unsatisfactory progress or another specific performance-related cause. Source
  • Retainage and interest generally release with final progress payment, subject to section 4(7)-(8). After 94% work-in-place, the original contractor may obtain release by furnishing the prescribed acceptable irrevocable letter of credit. Source

Primary sources

Sources reviewed 2026-09-30. This guide covers the projects and rules stated above.

Not legal advice. This is general legal information. Laws and project facts differ; confirm the applicable requirements for your project.

Back to Michigan contractor law · Retainage topic guide.

Related tools and support

Visit GC Experts for contractor business support. FedTrakker currently leads to the GC Experts site. For project-specific legal advice, find counsel.

Explore the $29 state packs and included templates.