Minnesota retainage

Retainage in Minnesota — Sources checked

Who and what this applies to

Private building/construction contract retainage under section 337.10 subdivision 4. That subdivision excludes public agencies and the identified professional-service contracts.

Thresholds and scope

Retainage may not exceed 5%; the section does not require retainage.

The rules

  • If the owner reduces retainage, the contractor must reduce downstream retainage at the same rate. Source
  • Release is due no later than 60 days after substantial completion, subject to the statutory allowed withholding. A contractor passes remaining retainage through within ten days after receipt, paying undisputed subs and supplying the required written explanation for a disputed withholding. Source
  • After substantial completion, permitted withholding is limited to 250% of known correction/completion cost plus the greater of 1% of contract value or $500 for final paperwork, with a written basis. Those amounts release within 60 days of completion/submission; warranty-work retainage is prohibited. Source

Primary sources

Sources reviewed 2026-09-30. This guide covers the projects and rules stated above.

Not legal advice. This is general legal information. Laws and project facts differ; confirm the applicable requirements for your project.

Back to Minnesota contractor law · Retainage topic guide.