Missouri retainage
Retainage in Missouri — Sources checked
Who and what this applies to
Covered public works under RSMo section 8.960, subject to its federal-funding and delayed-state-grant qualifications.
Thresholds and scope
Cap is normally 5%; the public owner may hold 10% when no bond is required because estimated cost does not exceed $50,000.
The rules
- Public construction-contract and subcontract retainage cannot exceed 5%, subject to the specified small-unbonded-contract exception. Source
- At least 98% of retainage, less lawful offsets/deductions, is payable within 30 days after substantial-completion acceptance and receipt of complete acceptable required documents; state-highway specifications may provide the stated alternative. Rejection requires a written explanation within 14 calendar days. Source
- Remaining minor items may support withholding of 150% of their value. Separate good-faith grounds for disputed/performance-related payment withholding remain under the statute. Source
Primary sources
Sources reviewed 2026-09-30. This guide covers the projects and rules stated above.
Not legal advice. This is general legal information. Laws and project facts differ; confirm the applicable requirements for your project.
Back to Missouri contractor law · Retainage topic guide.
Related tools and support
Visit GC Experts for contractor business support. FedTrakker currently leads to the GC Experts site. For project-specific legal advice, find counsel.