Retainage in Missouri — Sources checked

Who and what this applies to

Covered public works under RSMo section 8.960, subject to its federal-funding and delayed-state-grant qualifications.

Thresholds and scope

Cap is normally 5%; the public owner may hold 10% when no bond is required because estimated cost does not exceed $50,000.

The rules

  • Public construction-contract and subcontract retainage cannot exceed 5%, subject to the specified small-unbonded-contract exception. Source
  • At least 98% of retainage, less lawful offsets/deductions, is payable within 30 days after substantial-completion acceptance and receipt of complete acceptable required documents; state-highway specifications may provide the stated alternative. Rejection requires a written explanation within 14 calendar days. Source
  • Remaining minor items may support withholding of 150% of their value. Separate good-faith grounds for disputed/performance-related payment withholding remain under the statute. Source

Primary sources

Sources reviewed 2026-09-30. This guide covers the projects and rules stated above.

Not legal advice. This is general legal information. Laws and project facts differ; confirm the applicable requirements for your project.

Back to Missouri contractor law · Retainage topic guide.