Nebraska retainage

Retainage in Nebraska — Sources checked

Who and what this applies to

Construction Prompt Pay Act contracts excluding State contracts and specified state-paid aid projects; residential improvements of no more than four units are also excluded.

Thresholds and scope

Contract retainage rate cannot exceed 10%; further payments have a 5% limit after the qualifying 50%-complete point.

The rules

  • Section 45-1202 excludes State contracts and specified state-paid aid projects from contractor/subcontractor coverage. Source
  • Residential improvements of four or fewer units are excluded. Source
  • After the scope is 50% complete with contractual performance and satisfactory reasonable assurances of continued performance/financial responsibility, retainage on additional progress payments is at most 5%. Other withholding is limited to the listed reasonable contractual grounds; after substantial completion, it cannot exceed 125% of remaining work cost. Source
  • Owner retainage for compliant work releases within 45 days after substantial completion of the project/designated portion. Contractor pass-through is due within ten days of receipt when subcontract performance and payment conditions are satisfied. Source

Primary sources

Sources reviewed 2026-09-30. This guide covers the projects and rules stated above.

Not legal advice. This is general legal information. Laws and project facts differ; confirm the applicable requirements for your project.

Back to Nebraska contractor law · Retainage topic guide.

Related tools and support

Visit GC Experts for contractor business support. FedTrakker currently leads to the GC Experts site. For project-specific legal advice, find counsel.

Explore the $29 state packs and included templates.