Nebraska retainage
Retainage in Nebraska — Sources checked
Who and what this applies to
Construction Prompt Pay Act contracts excluding State contracts and specified state-paid aid projects; residential improvements of no more than four units are also excluded.
Thresholds and scope
Contract retainage rate cannot exceed 10%; further payments have a 5% limit after the qualifying 50%-complete point.
The rules
- Section 45-1202 excludes State contracts and specified state-paid aid projects from contractor/subcontractor coverage. Source
- Residential improvements of four or fewer units are excluded. Source
- After the scope is 50% complete with contractual performance and satisfactory reasonable assurances of continued performance/financial responsibility, retainage on additional progress payments is at most 5%. Other withholding is limited to the listed reasonable contractual grounds; after substantial completion, it cannot exceed 125% of remaining work cost. Source
- Owner retainage for compliant work releases within 45 days after substantial completion of the project/designated portion. Contractor pass-through is due within ten days of receipt when subcontract performance and payment conditions are satisfied. Source
Primary sources
- Neb. Rev. Stat. §45-1202
- Neb. Rev. Stat. §45-1207
- Neb. Rev. Stat. §45-1204
- Neb. Rev. Stat. §45-1203(3)
Sources reviewed 2026-09-30. This guide covers the projects and rules stated above.