Nevada retainage
Retainage in Nevada — Sources checked
Who and what this applies to
Covered private owner–prime agreements and Chapter 338 public works; Chapter 408 NDOT contracts are excluded from these public rules.
Thresholds and scope
Private contracted retainage is capped at 5% of payment; public percentages depend on completion and statutory defect withholding.
The rules
- Private contracted retention cannot exceed 5% of payment. Source
- The private owner–prime provisions exclude a natural-person owner’s single-family residence agreement and public works. Source
- Public bodies withhold 5% until 50% completion. Then satisfactory progress permits stopping/releasing retention. Continued retention without section 338.525 withholding is capped at 2.5% after release of half already retained; with that withholding, 5% and existing retention may continue. Source
- Chapter 408 Department of Transportation contracts are excluded. Source
Primary sources
Sources reviewed 2026-09-30. This guide covers the projects and rules stated above.