Nevada retainage

Retainage in Nevada — Sources checked

Who and what this applies to

Covered private owner–prime agreements and Chapter 338 public works; Chapter 408 NDOT contracts are excluded from these public rules.

Thresholds and scope

Private contracted retainage is capped at 5% of payment; public percentages depend on completion and statutory defect withholding.

The rules

  • Private contracted retention cannot exceed 5% of payment. Source
  • The private owner–prime provisions exclude a natural-person owner’s single-family residence agreement and public works. Source
  • Public bodies withhold 5% until 50% completion. Then satisfactory progress permits stopping/releasing retention. Continued retention without section 338.525 withholding is capped at 2.5% after release of half already retained; with that withholding, 5% and existing retention may continue. Source
  • Chapter 408 Department of Transportation contracts are excluded. Source

Primary sources

Sources reviewed 2026-09-30. This guide covers the projects and rules stated above.

Not legal advice. This is general legal information. Laws and project facts differ; confirm the applicable requirements for your project.

Back to Nevada contractor law · Retainage topic guide.