Prompt Payment in New York — Sources checked
Who and what this applies to
Covered private contracts, state-agency payments and covered local public works.
Thresholds and scope
Private coverage uses the Article 35-E threshold/exclusions; state and municipal deadlines have separate conditions.
The rules
- Private Article 35-E coverage starts at $150,000 aggregate project cost and excludes public work; 1–3-family dwellings; tracts of ≤100 one/two-family dwellings; residential projects ≤4,500 square feet; and qualifying publicly assisted residential projects under 75 units for households averaging 125% of HUD area median income. Source
- The private statutory invoice-review rule is 12 business days with required documentation; the contract generally controls except where the article prohibits variation. Written disapproval must identify the statutory grounds. Source
- Private owner payment is due within 30 days after approval; qualifying lender-contingent payment is due seven days after good funds, subject to section 756-d. Compliant downstream work is paid within seven days after good funds with required documents/waivers, subject to permitted withholding. Source
- Contract provisions changing the statutory payment rules specified in section 757(4) are void. Source
- Private late-payment interest is 1% per month or fraction, or the higher contractual rate. Source
- State-agency payment is generally due 30 calendar days excluding legal holidays after invoice receipt; qualifying small businesses using electronic invoices/requesting expedited treatment use 15 days, and highway final payments use 75. Statutory defects, inspection/audit, appropriation and compliance conditions can extend the date. Source
- Outside NYC, covered local public owners pay approvable requisitions within 30 days excluding legal holidays, or 45 where elected-official approval is required. Qualifying delayed state funding moves payment to ten days after its receipt; federal preemption applies. Source
- Covered state/public-owner contractors pass corresponding payments within seven calendar days, subject to statutory retention and unresolved claims/liens/judgments; lower tiers follow the same rule. Source
Primary sources
- N.Y. General Business Law §756(1)
- N.Y. General Business Law §756-a(2)
- N.Y. General Business Law §756-a(3)
- N.Y. General Business Law §757(4)
- N.Y. General Business Law §756-b(1)
- N.Y. State Finance Law §179-f(2)-(3), (6)
- N.Y. General Municipal Law §106-b(1)(a), (d), (3)
- N.Y. State Finance Law §139-f(2)
Sources reviewed 2026-09-30. This guide covers the projects and rules stated above.
Not legal advice. This is general legal information. Laws and project facts differ; confirm the applicable requirements for your project.
Back to New York contractor law · Prompt Payment topic guide.
Related tools and support
Visit GC Experts for contractor business support. FedTrakker currently leads to the GC Experts site. For project-specific legal advice, find counsel.