Oklahoma prompt payment

Prompt Payment in Oklahoma — Sources checked

Who and what this applies to

Covered written public construction contracts under the Fair Pay for Construction Act. Section 227 excludes highway, railroad, turnpike and one- through four-family dwelling contracts, and generally listed road/bridge/utility work unless part of a covered construction contract.

Thresholds and scope

Section 223 owner progress-payment rule applies to covered construction contracts exceeding $25,000.

The rules

  • Section 223 requires owner progress payments within 30 calendar days after submission of a proper invoice for work performed and properly stored materials. Source
  • For compliant work, §224 requires prime-to-subcontractor/supplier payment within 10 calendar days after corresponding receipt; subcontractor-to-lower-tier payment is due within seven calendar days. Source

Deadlines

Owner 30 days; prime downstream 10 days; lower-tier seven days.

Primary sources

Sources reviewed 2026-09-30. This guide covers the projects and rules stated above.

Not legal advice. This is general legal information. Laws and project facts differ; confirm the applicable requirements for your project.

Back to Oklahoma contractor law · Prompt Payment topic guide.

Related tools and support

Visit GC Experts for contractor business support. FedTrakker currently leads to the GC Experts site. For project-specific legal advice, find counsel.

Explore the $29 state packs and included templates.