Pennsylvania retainage

Retainage in Pennsylvania — Sources checked

Who and what this applies to

Private construction contracts under CASPA, excluding six or fewer residential units under simultaneous construction and material purchases for an owner’s own work. Government-owner projects instead use public-payment law.

Thresholds and scope

CASPA §9 supplies retainage-release and bond-substitution rules; it does not state a general percentage cap.

The rules

  • Amounts due for release on final completion must be paid within 30 days after final acceptance. Received retainage must be passed to subcontractors within 14 days. Source
  • At substantial completion of its own scope, a contractor or subcontractor may facilitate earlier release using an approved-surety maintenance bond for 120% of retained funds; statutory good-faith withholding conditions remain applicable. Source
  • Public-owner projects are governed separately under the Procurement Code, not CASPA. Source

Deadlines

Final-acceptance release 30 days; downstream 14 days.

Primary sources

Sources reviewed 2026-09-30. This guide covers the projects and rules stated above.

Not legal advice. This is general legal information. Laws and project facts differ; confirm the applicable requirements for your project.

Back to Pennsylvania contractor law · Retainage topic guide.

Related tools and support

Visit GC Experts for contractor business support. FedTrakker currently leads to the GC Experts site. For project-specific legal advice, find counsel.

Explore the $29 state packs and included templates.