Rhode Island mechanic's liens

Mechanic's Liens in Rhode Island — Sources checked

Who and what this applies to

Private construction liens under Title 34, Chapter 28; the statutory claimant, owner-consent and notice requirements govern.

Thresholds and scope

The notice ordinarily protects the preceding 200 days of furnishing; retainage has the special rule in §34-28-9.

The rules

  • Section 34-28-4 ordinarily requires both mailing the notice of intention by registered/certified return-receipt mail and recording its copy in the city/town land records within 200 days after the work or materials; follow all recipients and content requirements. Source
  • Section 34-28-10 requires both the enforcement complaint and lis pendens within 40 days after recording the notice. File the complaint the same day as the lis pendens or within seven days afterward. Source

Deadlines

Notice/mailing/recording generally 200 days; complaint and lis pendens 40 days.

Primary sources

Sources reviewed 2026-09-30. This guide covers the projects and rules stated above.

Not legal advice. This is general legal information. Laws and project facts differ; confirm the applicable requirements for your project.

Back to Rhode Island contractor law · Mechanic's Liens topic guide.

Related tools and support

Visit GC Experts for contractor business support. FedTrakker currently leads to the GC Experts site. For project-specific legal advice, find counsel.

Explore the $29 state packs and included templates.