Rhode Island prompt payment

Prompt Payment in Rhode Island — Sources checked

Who and what this applies to

Payments by Rhode Island state agencies to covered contractors, including building and highway construction.

Thresholds and scope

The required payment date generally is 30 working days after receipt of the proper invoice; statutory conditions can extend it.

The rules

  • Section 42-11.1-5 requires late-payment interest unless a listed exception applies, including lien/legal-process holds and interest below $10. Audit, appropriation, funding, federal-review and performance conditions can extend the required date by the time to resolve them. Source
  • Section 42-11.1-6 generally computes interest from the day after the required date through controller approval, at the Wall Street Journal prime rate prescribed there; interest accompanies principal and unpaid interest compounds monthly. Source

Deadlines

Generally 30 working days, subject to statutory extensions.

Primary sources

Sources reviewed 2026-09-30. This guide covers the projects and rules stated above.

Not legal advice. This is general legal information. Laws and project facts differ; confirm the applicable requirements for your project.

Back to Rhode Island contractor law · Prompt Payment topic guide.