Retainage in Rhode Island — Sources checked

Who and what this applies to

Contracts covered by §37-12-10.1: defined construction contracts and state/municipal public works, excluding contracts separately governed by §37-12-10. The §5-65-1 construction definition uses a $250,000 prime price and excludes one- through four-unit dwelling projects.

Thresholds and scope

Covered progress-payment retainage may not exceed 5%.

The rules

  • Section 37-12-10.1 requires the prime to submit substantial-completion notice within 14 days; the owner has 14 days to accept or reject with the required reasons, and silence produces deemed acceptance. Source
  • Ordinarily a retainage application may be submitted after 60 days from substantial completion or final resolution of its dispute; payment is due within 30 days after application, with the statutory state-revolving-fund cycle and seven-day-per-lower-tier variations. Section (f) permits specified withholding for defects, deliverables and incomplete work. Source

Deadlines

Notice 14 days; owner response 14 days; application/payment schedule as stated.

Primary sources

Sources reviewed 2026-09-30. This guide covers the projects and rules stated above.

Not legal advice. This is general legal information. Laws and project facts differ; confirm the applicable requirements for your project.

Back to Rhode Island contractor law · Retainage topic guide.

Related tools and support

Visit GC Experts for contractor business support. FedTrakker currently leads to the GC Experts site. For project-specific legal advice, find counsel.

Explore the $29 state packs and included templates.