South Carolina mechanic's liens

Mechanic's Liens in South Carolina — Sources checked

Who and what this applies to

Private building/structure liens under Chapter 29-5; public payment-bond claims are separate.

Thresholds and scope

The claimant must meet Chapter 29-5 eligibility, licensing and notice conditions.

The rules

  • Section 29-5-90 requires both filing the sworn statement in the county recording office and service on the owner within 90 days after the claimant’s last labor or furnishing; special alternatives apply if the owner cannot be found. Source
  • Section 29-5-120 requires both an enforcement suit and notice of pendency within six months after the claimant’s last labor or furnishing. Source

Deadlines

File and serve within 90 days; sue and file lis pendens within six months.

Primary sources

Sources reviewed 2026-09-30. This guide covers the projects and rules stated above.

Not legal advice. This is general legal information. Laws and project facts differ; confirm the applicable requirements for your project.

Back to South Carolina contractor law · Mechanic's Liens topic guide.

Get the South Carolina contractor pack

The South Carolina contractor law pack is $29 USD — a source-linked research snapshot covering licensing, mechanic's liens, retainage, prompt payment, prevailing wage, and Davis-Bacon, plus editable project-intake, payment-log, and source-review tools.

Get the South Carolina pack — $29 Free checklist preview

Browse all 50 state packs · Find counsel