South Carolina prompt payment
Prompt Payment in South Carolina — Sources checked
Who and what this applies to
Covered owner/contractor/subcontractor payments under Chapter 29-6. The chapter excludes residential homebuilders, residential improvements of 16 or fewer units, and private owners when the specific improvement is not financed by a nonowner.
Thresholds and scope
Section 29-6-50 allows specified private-contract changes only through a conspicuous express waiver by section number.
The rules
- For compliant performance, §29-6-30 requires payment of the undisputed owner pay request within 21 days after receipt and corresponding downstream payment within seven days after receipt. Source
- Section 29-6-40 preserves specified withholding grounds and reasonable retainage. Section 29-6-50 imposes 1% monthly/proportional interest from the due date only if notice of that section accompanied the pay request; permitted private-contract changes must satisfy its express waiver conditions. Source
Deadlines
Owner 21 days; downstream seven days.
Primary sources
Sources reviewed 2026-09-30. This guide covers the projects and rules stated above.
Back to South Carolina contractor law · Prompt Payment topic guide.