South Dakota mechanic's liens
Mechanic's Liens in South Dakota — Sources checked
Who and what this applies to
Persons furnishing labor, skill, services, equipment or materials for improvements at an owner's or contractor's request. This summary addresses ordinary building/improvement liens under section 44-9-1(1).
Thresholds and scope
Conditional extra notice applies to sub-subcontractors and suppliers to subcontractors when the statutory notice-of-commencement and posting procedures were invoked.
The rules
- File a verified lien statement with the county register of deeds within 120 days after the claimant's last work or furnishing. Before filing, mail a copy to the owner by registered or certified mail and attach the mailing receipt. Source
- If sections 44-9-50 and 44-9-51 were invoked, a sub-subcontractor or supplier to a subcontractor must give the section 44-9-53 notice within 60 days after its last furnishing to extend its lien. Send it to the identified contractor and copy the owner. Individual laborer claims below $2,000 are excepted. Source
- Generally assert the lien by complaint or answer within six years after the last item stated in the recorded claim. A served written demand to commence suit shortens the deadline to 30 days. Source
Deadlines
Recording: 120 days from last furnishing; conditional lower-tier notice: 60 days; enforcement: six years, or 30 days after statutory demand.
Primary sources
Sources reviewed 2026-09-30. This guide covers the projects and rules stated above.
Back to South Dakota contractor law · Mechanic's Liens topic guide.