Tennessee prompt payment
Prompt Payment in Tennessee — Sources checked
Who and what this applies to
TDOT road/bridge contracts incorporating the 2026 Standard Specifications; payments to subcontractors, material suppliers and haulers at all tiers.
Thresholds and scope
Payment clock runs from receipt of TDOT payment for the associated work.
The rules
- Section 109.02 requires the contractor to pay covered subcontractors, suppliers and haulers within 30 calendar days after corresponding TDOT payment; the same prompt-payment rules extend through subcontract tiers. Source
- The contractor documents monthly payments in AASHTOWare Project CRL; subcontractors and covered DBE/SBE material suppliers and haulers acknowledge posted payments within 14 calendar days. Source
Deadlines
Downstream payment 30 calendar days; covered posting acknowledgment 14 calendar days.
Primary sources
Sources reviewed 2026-09-30. This guide covers the projects and rules stated above.
Back to Tennessee contractor law · Prompt Payment topic guide.