Tennessee prompt payment

Prompt Payment in Tennessee — Sources checked

Who and what this applies to

TDOT road/bridge contracts incorporating the 2026 Standard Specifications; payments to subcontractors, material suppliers and haulers at all tiers.

Thresholds and scope

Payment clock runs from receipt of TDOT payment for the associated work.

The rules

  • Section 109.02 requires the contractor to pay covered subcontractors, suppliers and haulers within 30 calendar days after corresponding TDOT payment; the same prompt-payment rules extend through subcontract tiers. Source
  • The contractor documents monthly payments in AASHTOWare Project CRL; subcontractors and covered DBE/SBE material suppliers and haulers acknowledge posted payments within 14 calendar days. Source

Deadlines

Downstream payment 30 calendar days; covered posting acknowledgment 14 calendar days.

Primary sources

Sources reviewed 2026-09-30. This guide covers the projects and rules stated above.

Not legal advice. This is general legal information. Laws and project facts differ; confirm the applicable requirements for your project.

Back to Tennessee contractor law · Prompt Payment topic guide.

Related tools and support

Visit GC Experts for contractor business support. FedTrakker currently leads to the GC Experts site. For project-specific legal advice, find counsel.

Explore the $29 state packs and included templates.