Washington prompt payment
Prompt Payment in Washington — Sources checked
Who and what this applies to
State and local public contracts; downstream public-work payments under RCW 39.04.250.
Thresholds and scope
Public-invoice timing is separate from the ten-day downstream rule.
The rules
- RCW 39.76.011 ordinarily requires payment by the contractual date, no later than 30 days after the later of a proper invoice or receipt of goods/services. For grant- or federally funded contracts, satisfactory work is payable within 30 days after the compliant request or receipt of the funding, whichever is later. Source
- For public-work payment requests, RCW 39.76.011(2)(b) requires written notice within eight working days stating the performance or invoice problem and remedial steps if payment will be withheld. Source
- RCW 39.04.250 requires a contractor or subcontractor receiving public-work payment to pass each subcontractor’s attributable share within ten days. A good-faith dispute permits withholding no more than 150% of the disputed amount; parties outside the dispute remain entitled to prompt full payment. Source
Deadlines
Public owner: generally 30 days; downstream: ten days after receipt.
Primary sources
Sources reviewed 2026-09-30. This guide covers the projects and rules stated above.
Not legal advice. This is general legal information. Laws and project facts differ; confirm the applicable requirements for your project.
Back to Washington contractor law · Prompt Payment topic guide.