Washington retainage
Retainage in Washington — Sources checked
Who and what this applies to
Public-improvement contracts under RCW 60.28.011, subject to the statute’s financing exceptions.
Thresholds and scope
Ordinary public-contract retainage may not exceed 5% of money earned.
The rules
- RCW 60.28.011(1)(a) reserves up to 5% as a trust fund for contract claimants and the specified state taxes and assessments. Federally funded transportation contracts instead use the contract bond protection under subsection (1)(b). Source
- Under subsection (3), a contractor may request reduction of retainage to 100% of the value of work remaining. The ordinary release deadline is 60 days after completion of all contract work, subject to Chapter 39.12 and the statutory claim and tax protections. Source
- Under subsection (3)(a), after completing all work other than landscaping, the contractor may request release; payment follows 60 days after that request, with continuing retention of 5% of the landscaping earnings and the same statutory conditions. Source
- Subsection (10) separately excludes contracts funded partly or wholly by the Farmers Home Administration and subject to its regulations from subsections (1)-(9). Source
Deadlines
Release depends on completion and satisfaction of statutory wage, tax, and claim conditions.
Primary sources
Sources reviewed 2026-09-30. This guide covers the projects and rules stated above.
Back to Washington contractor law · Retainage topic guide.
Related tools and support
Visit GC Experts for contractor business support. FedTrakker currently leads to the GC Experts site. For project-specific legal advice, find counsel.