Wisconsin prompt payment

Prompt Payment in Wisconsin — Sources checked

Who and what this applies to

State-agency payment protections under Wisconsin Statutes 16.528 and construction-contract conditions under 779.135.

Thresholds and scope

Section 16.528 has defined agency coverage and federal-funding, contract, and good-faith-dispute exceptions.

The rules

  • Section 16.528(2) ordinarily treats payment on current covered state orders/contracts as timely by the later of the proper invoice’s specified date or 30 days after the later of invoice receipt and receipt/acceptance of goods or services. The late-interest calculation begins on day 31 under the statute’s conditions. Source
  • Section 16.528(2m) requires prime contractors to pay subcontractors for satisfactory work within seven days after receiving the agency payment and imposes late interest from day eight; the payment and interest rules pass to lower tiers. A properly notified good-faith dispute is excepted. Source
  • Section 779.135(3) voids a construction term making owner payment a condition precedent to the prime contractor paying a subcontractor, supplier, or service provider. It expressly allows terms that delay payment until the prime receives payment. Source

Deadlines

Covered state downstream payments: seven days after receipt; private construction contract terms must comply with Section 779.135.

Primary sources

Sources reviewed 2026-09-30. This guide covers the projects and rules stated above.

Not legal advice. This is general legal information. Laws and project facts differ; confirm the applicable requirements for your project.

Back to Wisconsin contractor law · Prompt Payment topic guide.

Related tools and support

Visit GC Experts for contractor business support. FedTrakker currently leads to the GC Experts site. For project-specific legal advice, find counsel.

Explore the $29 state packs and included templates.